[shaunyc.org logo]

House Building - Progress

HOME >> PROJECTS >> HOUSEBUILDING - PROGRESS

 


We're building a house!

This page shows how the building work is progressing.


Current state - 18th September 2005



18th September 2005

The front garden is nearing completion.


6th June 2005

We've moved in!
Fences have been erected, and a garage door added.


14th May 2005

The inside of the house is finished. Outside, a retaining wall makes the upper section of the front yard level. The remainder of the driveway is finished.


30th April 2005

Carpets and blinds have been installed. Electrical and plumbing is complete.


20th March 2005

Bathrooms are complete. The top section of the driveway is down.


12th December 2004

[15th January 2005]
Lockup! The windows, exterior and interior doors have been installed. Inside, ceilings and cornices are all in place, but still need painting.

The kitchen has been installed. Compare the original design with the finished kitchen.


5th December 2004

[5th December 2004]
The roof is on, and the outside of the house is finished. Inside, plastering, plumbing and electrical wiring are finished.


14th November 2004

The roof frame is finished, gutters and downpipes have been added. Inside, electrical wiring and sockets are in place.


7th November 2004

7th November 2004
The roof frame is largely in place.


24th October 2004

24th October 2004
All brickwork, interior and exterior, is now finished.


17th October 2004

17th October 2004
Lots of progress since last weekend. The garage walls appeared first, and then over the course of two days, all of the exterior walls were built. Window frames are in place, and a about half of the interior of the double-brick walls have been built.


10th October 2004

10th October 2004
The interior bricks have been delivered, but the real sign that things are about to happen is that the portable toilet has arrived on site... The bricklayers have arrived too. A single layer of bricks has been laid all around the outside of the slab, the garage outline is in place, and part of the east wall is taking shape.


2nd October 2004

2nd October 2004
There was a big delay after pouring the slab before all of the bricks could be delivered, but at long last the bricks, window frames and door frames have arrived, and bricklaying should start soon. Still missing the interior bricks.


7th August 2004

7th August 2004
Concrete has been poured into the outline.


31st July 2004

31st July 2004
The outline of the house has been marked out in the sand, and the plumbing pipes have been laid in the ground for the laundry, bathrooms and kitchen. The outline is covered with polythene, and steel reinforcement grids are laid on top, ready for the concrete to be poured.


18th July 2004

18th July 2004
First sign of building activity. The block has been cleared of weeds, built up about 30cm, and leveled.